DONALDSONVILLE, La. — A Louisiana community group and the Sierra Club filed a lawsuit Friday seeking to overturn the state air permit issued for a proposed Hyundai-POSCO steelmaking plant in the industrial corridor along the Mississippi River known as Cancer Alley.
RISE St. James Louisiana and the Sierra Club, the national environmental organization, are challenging the Louisiana Department of Environmental Quality’s decision to grant the permit. The groups argue the permit must be vacated because the agency did not conduct an environmental justice analysis or fully weigh cleaner technologies and the environmental costs of added pollution, which they say the Louisiana Constitution and the federal Clean Air Act require.
The petition, filed Nov. 20, asks the court to reverse the agency’s final decision. The allegations have not been tested in court.
According to the Sierra Club, the plant is one of several polluting facilities planned for the 17,000-acre Riverplex MegaPark in Ascension Parish. The group said the surrounding area already carries a toxic air pollution burden greater than 96% of the rest of the country. It said the final permit allows the facility to release large amounts of greenhouse gases, nitrogen oxides, particulate matter, carbon monoxide, lead, mercury, ammonia and other pollutants, even after Hyundai Steel made some changes to its application under public pressure.
“By refusing to conduct an environmental justice analysis, consider cleaner technologies like electrifying components and replacing dirty gas with green hydrogen, or consider any environmental costs of Hyundai’s pollution, LDEQ has failed to perform the most basic function of its role,” said Andrea Issod, a senior attorney for the Sierra Club.
Mekaylyn Lavigne, the Modeste coordinator for RISE St. James, said residents of her community deserve to know the full impact of the mill planned near her home. “The court should make LDEQ go back to the drawing board on this permit to disclose all the impacts and use the cleanest technologies to reduce pollution,” she said.
The petition makes several claims, according to the groups. They say Hyundai initially included an environmental justice analysis in its application but later removed it without explanation. They also contend the agency assessed no environmental costs in its cost-benefit review, released its public-trust analysis only after the public comment period closed, and did not perform the case-by-case review required to evaluate electrified equipment or blending in green hydrogen.
The groups further challenge the agency’s finding that the plant would not cause or contribute to violations of federal ozone standards, arguing that regulators relied on a monitor in the Dutchtown neighborhood instead of a closer regional monitor in Carville.
The Sierra Club said it and other groups filed comments with the agency throughout 2026 pointing out what they described as errors and omissions in the permit application.
This report is based on information from the Sierra Club.
Source: Sierra Club